Panel Base Connector – P
Panel Base Connector – P*
Eliminate misaligned embed plates and field welding by
bolting panels directly to the foundation
The Panel Base Connector-P is easy to position
and fasten at the bottom edge of the form. It can be
placed in either a face-up or face-down orientation
depending on the forming and handling preference.
The high-strength, purpose designed drill-in 3/4”x10”
screw anchor provides an immediate and secure
connection when tightened. There is no grout set-up
or wait time.
The connection is centered in the concrete panel,
minimizing moment and eccentric forces in the
design, and resisting in-plane tension and out-of-
plane shear forces.
Foam thickness can be increased to center PBC-P in wall.
The connection provides a nominal capacity in
excess of 10 Kips for tension, meeting the applicable
ACI requirements.
The relatively small access area is easy to grout,
providing complete embedment and encapsulation
for corrosion protection.
Panel Base Connector Kit
Part No. Description
SBPBC10-P 10” Panel Base Connector – P Kit w/ 3/4” x 10” Screw Anchor
SBPBC12-P 10” Panel Base Connector – P Kit w/ 3/4” x 12” Screw Anchor
* 12” Screw Anchor available if spacing between bottom of panel and footing is more than 2”.
Meets ACI integrity requirements of ACI-318 -11
16.5.1.3(b) ACI318-14 16.2.4.3(b), ACI-318-19
16.2.4.3 (b), and ACI 551.2R-15 Chapter 8.
Note: 7” Screw Anchor
engagement required
* Patent No.: U.S. 11,891,790
2525 Armitage Ave
Melrose Park, IL 60160
708-493-9569
www.surebuilt-usa.com
09/26Basic Installation
1. Position and fasten the Panel Base Connector-P to the desired
location(s) in the bottom edge of panel formwork using the holes
provided or hold up for upside wall projection.
2. Cast, lift, handle and erect the completed panel on the concrete
footing or foundation as typical.
3. Remove the foam cover from the face of Panel Base Connector-P.
4. Through the opening of the Panel Base Connector-P, drill a
minimum 3/4” x 7” hole in foundation, using a 3/4” bit, into the
footing or foundation.
5. Clean the concrete dust from each hole.
6. Place the 3/4” x 10” screw anchor though the Panel Base
Connector-P into the footing or foundation.
7. Torque anchor into the footing or foundation with a maximum of
150 ft.-lbs. Do not over-torque anchor.
8. Grouting cavity or patching face of panel is not required and is
optional.
10” PBC-P
Position and fasten
the connector along
the bottom edge of the
panel formwork.
Position and chair
the connector along
the top edge of the
panel formwork.
Drill a 3/4” x 7” hole, using
a 3/4” x 24” bit, through the
opening of the connector into
the footing or foundation.
Place a 3/4” x 10” screw
anchor though the connector
and footing or foundation,
then torque to 150 ft-lbs.
Grouting cavity or patching
face of panel is not required
and is optional.Installation Detail
EDGE DISTANCES FOR ANCHORS TO BE
PER SPECIFICATIONS OF THE ANCHOR
MANUFACTURER. RECOMMENDED
MINIMUM EDGE DISTANCE IS 9″.
WALL PANEL
X”
7″ MIN.
CAST IN PLACE FOUNDATION
APPROX. DIMENSION FOR THE DEPTH
OF THE ANCHORAGE ASSUMING A 10″
LONG SCREW ANCHOR & A 1″-2″ GROUT
JOINT. VERIFY FOOTING DEPTH WITH
THE STRUCTURAL DRAWINGS. MINIMUM
DISTANCE TO BOTTOM OF FOOTING TO
BE PER SPECIFICATIONS OF THE
ANCHOR MANUFACTURER.
4″
NON-SHRINK, NON-METALLIC GROUT
4″
COORDINATE WITH EOR/GC TO HAVE REINFORCEMENT
ONLY IN CORNERS, OR TO SHIFT ANY INTERMEDIATE
REINFORCEMENT OUT OF THE ANCHORAGE ZONE.
DIMENSIONS SHOWN ARE MINIMUM DISTANCE TO SHIFT
OVER THE REINFORCEMENT.
Repair Concept
PBC-P REPAIR CONCEPT
IN CASE 3 4“Ø x 10” CONCRETE SCREW
ANCHOR HITS REBAR.
2
1 2
3
4
1. PLACE 1/2″ x 3″ x 15″ STRIP UNDER PANEL.
2. WELD STRIP (1/4″ x 3″) TO BOTTOM OF PBC-P.
(3.7 KIPS/INCH)
3. DRILL (2) 3/4″Ø HOLES IN FOOTING, 5″ DEEP.
4. PLACE 3/4″Ø x 6″ CONCRETE SCREWS IN FOOTING.
NOTE: CLEAN/PREPARE AREA FOR WELDING.
COVER WELD AREA FOR CORROSION AFTER WELDING.
DISCLAIMER:
The repair information provided is for general guidance only & is not intended as a substitute for
professional engineering review or approval. The suitability, effectiveness & safety of any repair
should be evaluated & verified by a qualified engineer based on the specific project conditions,
structural requirements & applicable codes & standards. The responsibility for ensuring the
adequacy of the repair remains with the project engineer & other relevant professionals. The
manufacturer & distributor assume no liability for improper use, application or reliance on this
information.
The following repair concept has been provided to assist in the repair of a PBC-P connection if the
hole cannot be drilled to appropriate depth or if the bolt in not able to be fully installed or reach the
recommended torque levels.
Capacity of repair strength to be determined by project engineer based on foundation conditions &
criteria.